PMP Formulas Cheat Sheet: Every Formula With Worked Examples

The PMP formulas worth knowing fall into eight groups: earned value management (EVM), three-point estimating, schedule float, communication channels, risk, procurement incentive contracts, agile forecasting, and project selection finance. Each table below gives the formula, the question it answers and how to read the result, followed by worked examples with real numbers.

An honest note before you memorize anything: the current exam, built on the July 2026 Examination Content Outline, has fewer pure calculation questions than older formats. Expect some calculations, mostly EVM, and a lot of interpretation. Many questions hand you a CPI or SPI that is already calculated and ask what it means or what the project manager should do next. Knowing how to read a result matters more than computing it quickly.

Earned value management: the core terms

Every EVM formula uses four inputs. Get these definitions straight first.

  • PV (planned value): the budgeted value of the work scheduled to be done by now.
  • EV (earned value): the budgeted value of the work actually completed by now.
  • AC (actual cost): what the completed work has actually cost.
  • BAC (budget at completion): the total approved budget for the work.

Two memory aids cover most of the section. Variances and indices always start with EV. For variances (subtract), negative is bad. For indices (divide), below 1.0 is bad.

Performance: variances and indices

FormulaWhat it answersHow to read the result
CV = EV - ACAre we over or under budget for the work actually done?Negative means over budget, positive means under budget, zero means on budget.
SV = EV - PVHave we completed more or less work than planned by now?Negative means behind schedule, positive means ahead. It is expressed in money, not days.
CPI = EV / ACHow much value do we earn for each dollar spent?Below 1.0 is over budget (less than $1 of work per $1 spent). Above 1.0 is under budget.
SPI = EV / PVHow fast are we progressing compared with the plan?Below 1.0 is behind schedule, above 1.0 is ahead.

Forecasting: EAC, ETC, VAC and TCPI

FormulaWhat it answersHow to read the result
EAC = BAC / CPIWhat will the whole project cost if current cost performance continues?Use when the variance so far is typical and expected to persist.
EAC = AC + (BAC - EV)What will it cost if the remaining work goes exactly to the original plan?Use when the variance was atypical: a one-time event that will not repeat.
EAC = AC + bottom-up ETCWhat will it cost if we re-estimate the remaining work from scratch?Use when the original estimate is no longer valid (scope or assumptions changed).
EAC = AC + (BAC - EV) / (CPI × SPI)What will it cost if both cost and schedule performance drive the remaining work?Use when a firm deadline means schedule pressure will also affect cost.
ETC = EAC - ACHow much more money do we need to finish?Compare with remaining funding; a gap needs escalation and change control.
VAC = BAC - EACHow far over or under budget will we be at the end?Negative means an expected overrun, positive means an expected underrun.
TCPI = (BAC - EV) / (BAC - AC)What cost efficiency must the remaining work achieve to finish on the original budget?Above 1.0 means the team must perform better than planned. Far above the current CPI usually means the BAC is no longer realistic.
TCPI = (BAC - EV) / (EAC - AC)What efficiency is needed to finish on an approved new EAC?Use once a revised EAC has been approved through change control.

Which EAC formula should you pick?

Exam questions signal the right EAC through the story, not the numbers. Read for these cues:

  • "Current performance is expected to continue" or no reason to expect change: use BAC / CPI.
  • "A one-time problem," "an unusual event," "will not recur": use AC + (BAC - EV).
  • "The original estimate was fundamentally flawed" or assumptions changed: use AC + bottom-up ETC.
  • A fixed deadline or a note that schedule performance will also affect cost: use AC + (BAC - EV) / (CPI × SPI).

For the interactive version, with a calculator that shows every metric as you change PV, EV, AC and BAC, use the EVM study guide and calculator.

Worked example 1: a project over budget and behind schedule

BAC is $200,000. At the month 4 status review, PV is $80,000, EV is $70,000 and AC is $87,500.

  • CV = 70,000 - 87,500 = -$17,500 (over budget).
  • SV = 70,000 - 80,000 = -$10,000 (behind schedule).
  • CPI = 70,000 / 87,500 = 0.80: the project earns 80 cents of work per dollar spent.
  • SPI = 70,000 / 80,000 = 0.875: work is progressing at 87.5% of the planned rate.
  • EAC (typical) = 200,000 / 0.80 = $250,000; ETC = 250,000 - 87,500 = $162,500; VAC = 200,000 - 250,000 = -$50,000.
  • EAC (atypical) = 87,500 + (200,000 - 70,000) = $217,500.
  • EAC (CPI × SPI) = 87,500 + 130,000 / 0.70 = about $273,214.
  • TCPI to BAC = 130,000 / 112,500 = about 1.16. The team must improve from 0.80 to 1.16, which is unlikely without a change.
  • TCPI to the typical EAC = 130,000 / 162,500 = 0.80, which matches the current CPI.

The interpretation is what the exam rewards: the three EACs range from $217,500 to about $273,214 depending on the assumption, and hitting the original budget would need performance the team has not shown. The project manager should analyze the root cause, discuss options with the sponsor and route any budget or baseline change through integrated change control.

One more SPI subtlety: SV and SPI are measured in money. On a predictive project, EV eventually equals PV and BAC once all work is done, so SPI drifts back toward 1.0 near the end even if the project finishes late. Late in a project, check the schedule itself rather than relying on SPI.

Estimating: PERT, triangular and standard deviation

FormulaWhat it answersHow to read the result
PERT mean = (O + 4M + P) / 6What is the expected duration or cost, weighting the most likely value?Pulled toward M. Use when the question says PERT, beta distribution or weighted average.
Triangular = (O + M + P) / 3What is the simple average of the three estimates?Gives equal weight to each point. Use when the question says triangular or simple average.
PERT SD = (P - O) / 6How uncertain is this estimate?A larger value means a wider spread and more uncertainty. Compare activities by their SD.

Worked example 2: a three-point estimate

An activity has an optimistic estimate of 4 days, a most likely estimate of 7 days and a pessimistic estimate of 16 days.

  • PERT mean = (4 + 4 × 7 + 16) / 6 = 48 / 6 = 8 days.
  • Triangular = (4 + 7 + 16) / 3 = 27 / 3 = 9 days.
  • Standard deviation = (16 - 4) / 6 = 2 days, so one standard deviation either side of the PERT mean is 6 to 10 days.

The pessimistic tail pulls both averages above the most likely value. The triangular result is higher because it gives the 16-day pessimistic case the same weight as the most likely case.

Schedule: total float and free float

FormulaWhat it answersHow to read the result
Total float = LS - ES = LF - EFHow long can this activity slip without delaying the project end date?Zero on the critical path in a normal network. Negative float means the path cannot meet an imposed date.
Free float = ES of successor - EF of activityHow long can this activity slip without delaying the next activity?Free float is never more than total float. Zero means any delay pushes the successor.

Example: an activity has ES 5, EF 9, LS 8 and LF 12. Total float is 8 - 5 = 3 days. Its only successor has an ES of 11, so free float is 11 - 9 = 2 days. Some textbooks start networks at day 0 and others at day 1; a question will use one convention consistently, so follow it rather than switching. The critical path is the longest path through the network, and the exam cares more about what you do when a critical activity slips (for example crashing or fast tracking, with their cost and risk trade-offs) than about drawing the network. The schedule management guide covers those responses.

Communication channels and risk

FormulaWhat it answersHow to read the result
Channels = n(n - 1) / 2How many communication paths exist between n people?Grows much faster than team size. Count everyone, including the project manager.
EMV = probability × impactWhat is the probability-weighted value of a risk?Threats are negative, opportunities positive. Sum EMVs to size a contingency reserve or compare options.

Worked example 3: channels, EMV and a decision tree

Channels. A team of 8 people (including you) has 8 × 7 / 2 = 28 channels. Adding 4 people gives 12 × 11 / 2 = 66 channels, an increase of 38. That growth is why larger teams need a deliberate communications management plan.

EMV. A threat has a 30% probability of a $40,000 penalty: EMV = 0.30 × -40,000 = -$12,000. An opportunity has a 20% probability of saving $25,000: EMV = +$5,000. Combined EMV is -$7,000.

Decision tree. Option A costs $120,000 and returns $300,000 if demand is high (60%) or $150,000 if demand is low (40%). Its expected return is 0.6 × 300,000 + 0.4 × 150,000 = $240,000, so its net value is $120,000. Option B costs $50,000 and returns $180,000 (60%) or $130,000 (40%): expected return $160,000, net value $110,000. Choose Option A, because $120,000 is higher than $110,000. The logic is always the same: calculate the EMV of each branch, subtract the cost of the decision, then pick the best net value (highest for gains, lowest for costs). See the risk management guide for how EMV feeds contingency reserves.

Procurement: point of total assumption (PTA)

PTA applies to fixed price incentive fee (FPIF) contracts. The terms matter more than the arithmetic:

  • Target cost and target fee add up to the target price.
  • Ceiling price is the most the buyer will pay.
  • Share ratio (buyer/seller, for example 70/30) says how cost overruns and underruns are split. The buyer's share is the first number.

PTA = ((ceiling price - target price) / buyer's share ratio) + target cost. It is the actual cost at which the seller starts to absorb every additional dollar, because the buyer's payment has reached the ceiling.

Example: target cost $100,000, target fee $10,000 (target price $110,000), ceiling price $120,000, share ratio 70/30. PTA = (10,000 / 0.70) + 100,000 = about $114,286. Check: at that cost the overrun is about $14,286, the seller absorbs 30% of it (about $4,286), the fee falls to about $5,714, and cost plus fee equals the $120,000 ceiling. Above $114,286, the seller pays 100% of further overruns. The procurement guide explains how contract type shifts risk between buyer and seller.

Agile forecasting: velocity

Sprints remaining = remaining story points / velocity, rounded up to whole sprints. With 240 points left and an average velocity of 30 points, the team needs 8 sprints; with two-week sprints that is about 16 weeks. Use a recent average or a range (best and worst recent sprints) rather than a single sprint. Velocity belongs to one team and its own estimating scale, so never use it to compare teams or as a productivity target. Scenario questions on this topic are in the agile and hybrid guide.

Business and finance concepts for project selection

These mostly appear at concept level: you need to know which number to prefer, not how to build a discounted cash flow model.

FormulaWhat it answersHow to read the result
PV = FV / (1 + r)^nWhat is a future amount worth today at discount rate r over n periods?Money received later is worth less today. Higher rates and longer periods shrink PV.
NPV (concept)Do the discounted benefits exceed the investment?Positive NPV adds value; choose the highest NPV. Project length is already reflected, so do not adjust for it again.
IRR (concept)At what discount rate does NPV equal zero?Higher is better. Compare against the organization's required rate of return.
BCR (concept)How many units of benefit do we get per unit of cost?Above 1.0 means benefits exceed costs; choose the highest ratio.
ROI (concept)How large is the net gain relative to the investment?Higher is better. It ignores timing unless the benefits are discounted.
Payback period (concept)How long until the investment is recovered?Shorter is better for liquidity and risk, but it ignores time value and cash flows after payback.

Example: $121,000 received in two years at a 10% discount rate is worth 121,000 / 1.21 = $100,000 today. Two related ideas show up in selection questions: sunk costs (money already spent) should not influence the decision, and opportunity cost is the value of the best option you did not choose.

Worked example 4: reading results, not computing them

A typical modern question reads: "Midway through the project, CPI is 1.05 and SPI is 0.82. What should the project manager do first?" No arithmetic is needed. The project is under budget but behind schedule, so the useful response is to analyze why work is behind (resource availability, dependencies, scope growth) and then consider options such as fast tracking or adding resources, weighing their cost and risk, before changing any baseline through change control. The trap answers usually celebrate the cost result or jump straight to a baseline change.

Common formula mistakes

  • Starting a variance or index with AC or PV instead of EV.
  • Using BAC / CPI when the question says the variance was a one-time event.
  • Reading a negative VAC as savings. Negative VAC means a forecast overrun.
  • Forgetting to count yourself in n for communication channels.
  • Using PERT when the question asks for a triangular (simple) average, or the reverse.
  • Using the seller's share instead of the buyer's share in the PTA formula.
  • Comparing velocity across teams, or treating it as a commitment.
  • Choosing projects by payback period when NPV or IRR is given; NPV is the stronger measure.

How to practice formulas efficiently

Learn each formula together with the decision it supports. Write the cheat sheet from memory once a week, then spend most of your time on scenario questions where the numbers are already given. The cost management guide covers reserves and budgets, and the PMP glossary defines the terms used in this sheet.

Frequently asked questions

How many formulas are on the PMP exam?
PMI does not publish a formula list or a count of calculation questions. Expect some calculations, mostly earned value, and more questions that ask you to interpret a result that is already given.
Which PMP formulas are the most important?
Earned value formulas come first: CV, SV, CPI, SPI, the four EAC variants, ETC, VAC and TCPI. After those, focus on three-point estimates, float, communication channels and EMV.
Which EAC formula should I use on the exam?
Let the scenario decide. Divide BAC by CPI when current performance will continue, add the remaining budgeted work to AC when the variance was a one-off, and add a new bottom-up ETC to AC when the original estimate is no longer valid. Use the CPI times SPI version when schedule pressure will also drive cost.
Is a CPI below 1 good or bad?
It is bad for cost: the project is getting less than one dollar of work for every dollar spent. An SPI below 1 likewise means work is behind the plan.
What is the difference between PERT and triangular estimates?
PERT gives the most likely estimate four times the weight of the optimistic and pessimistic values, while the triangular estimate is a simple average of all three. Use whichever method the question names.
Do I need to calculate NPV and IRR for the PMP?
Usually not. Know how to compare options: a higher NPV, a higher IRR, a benefit-cost ratio above 1 and a shorter payback period are preferred, and sunk costs should be ignored.

Test whether you can interpret these results under exam conditions. Try the free PMP practice questions with full explanations, no signup needed.

FREE MOCK EXAMTest yourself on the July 2026 format.180 questions, 240 minutes, AI debrief included.Start free

PMP Exam Lab is an independent exam preparation platform and is not affiliated with, endorsed by, or connected to PMI.

PMP Exam Lab does not guarantee exam success or certification.